New Gold says it’s still on target for the start of production at its gold mine north of Barwick this September.
In an update, the company says all of the key structural components of the process facilities have been finalized while the installation of mechanical, piping, electrical and instrumentation are all close to completion.
The primary crusher and conveyor system was also put into operation in mid-May.